Adair PDB regular Nov. 2006 report: Completion March 2008

Board formally accepts Pyles Excavating low bid. Lot may be leveled by weekend or early next weekend, Branscum spokesman says. Bids can't be let by first of the year, architect tells Dennis Loy, who said "We're in a footrace against costs," but agrees that slower pace may be advisable. "We don't want to gom it (the courthouse) up," (caused by haste), he says. Realistic start date: Spring, 2007. Realistic completion date: Around March 31, 2008.
New drawings: Rear, side elevations

By Ed Waggener

A realistic outlook for the opening of the new Adair County Justice Center is early spring, 2008, Bing Ewen, chief architect for the project for DLZ, Frankfort, said last night.

But excitement at the site may be as close as this weekend, Jeff Cook, with the project's construction manager, Branscum Construction of Russell Springs, said after the Adair County Project Development Board awarded the contract for demolition of the remaining buildings on the Campbellsville & Merchant Streets site.

The board met last night, Tuesday, October 24, 2006, at 5:00pm, with five of the board's six members finally present.



Judge Jerry Vaughan, chairman of the board, called the meeting into session with only three members present. But a quorum was established by the presence of Jeff Lilly, the Administrative Office of the Courts (AOC), standing in as a board member, a position he can assume to 1) Establish a quorum, and 2) Vote in the case of a tie. With Lilly, the quorum included Judge Vaughan, First District Adair County Magistrate Roger Stephens, and Columbia Attorney Marshall F. Loy.

Doug Teague, the regular AOC member of the panel, had sent word that he would be absent, and Judge James C. Weddle and Adair County Circuit Court Clerk Dennis Loy had been held up in Tuesday's heavy Circuit Court Docket. However, before any action was taken, the Judge and County Court arrived and a quorum of regular members was present to vote on all issues before the PDB.

The Board voted unanimously to accept Branscum Construction's recommendation to accept the low bid of Pyles Excavating, Inc., Columbia, KY. "Anticipating the acceptance of their bids," Branscum Construction's Jeff Cook said, "they've already gone ahead with preparation of permit applications and they think they can get underway no later than this weekend or early next weekend."

The bids, which had been opened Friday, October 20, 2006, were as follows:
1. Pyles Excavating, Inc.. Columbia, KY, $13,500.
2. Leo Curry, Greensburg, KY, $17,200.
3. Ivan Greer, Knifley, KY, $17,600.
4. Egypt Construction, Columbia, KY $30,000.
The demolition should not take long, when it happens. Architect Bing Ewen estimated 20 minutes for Adair Florist and 25 for Adair Muffler. The third building from the site, has been leveled, with salvaged materials stacked on the Fairgrounds ST lot where it will be resurrected. It was occupied by Sign America and First Realty & Auction Company, which is now open at their new location in the Meadow Hill Inn/Walker Florist Building at the NE corner of Burkesville ST and Frazier Avenue.

Project 6 months behind, which is normal, DLZ, AOC says

Circuit Court Clerk Dennis Loy, concerned that soil borings weren't done in the last two weeks, wanted to know if there were any way the construction project could be speeded up.

"We're in a footrace against building price increases," Clerk Loy said. "I thought the soil borings would be done while we were bidding the demolition."

Bing Ewen agreed that time is a factor in the final cost of the building, but said his firm had made a decision to have the buildings removed before doing the soil borings.

"We are six months behind schedule," he said, "but that is because we were six months behind schedule in securing the site."

Jeff Lilly, representing the AOC, responded by saying, "I want to say this in defense of DLZ. This project is where most of the similar projects around the state are at this stage. Delays happen." He said that Adair County's Courthouse is closer to schedule than Hart County's and other projects under his purview.

Mr. Ewen responded that he could cite a "nightmare" scenario, saying that one of DLZ projects, started when the Adair County one was, still doesn't have a site purchased.

The answers soothed Clerk Loy a bit. "We don't want to gom it up. We'd rather see it done right than done quickly."

After the meeting, Mr. Ewen said he thought that the contracts would be left in early 2007. "It will take about 12 months to complete," he said, and agreed that the project should be complete around the end of March in 2008.

Design modifications presented

Megan Campbell-Smith reviewed design modifications since the last meeting. The survey of the site, she said, showed that the lot was 20 feet shorter on one side, but longer on another, and that it necessitated modifications, mostly in the parking spaces available, with four fewer public, two fewer staff, and one more secured parking slots.

Lightly attended, brief

The meeting was brief, lightly attended lasting only 32 minutes, and was over at 5:32pm CT. The gallery consisted of Seventh District Magistrate and County Judge candidate Terry Farris and one member of the media. Deputy Judge Gale Cowan acted as secretary for the meeting.

Next meeting set

The next meeting of the Adair Project Development Board will be Tuesday, November 28, 2006, at 5:00pm CT, in the basement of the Adair Annex Building.End of report on October 24, 2006, regular PDB meeting


About your Adair County Justice Center Project Development Board (PDB)


The Adair County Justice Center Project Development Board includes the chairman, Adair County Judge Executive Jerry Vaughan, and Adair County District 1 Magistrate Roger Stephens, the PDB includes Attorney Marshall Loy, Circuit Court Judge Jim Weddle, Adair County Court Clerk Dennis Loy. Douglas Teague, Administrative Office of the Courts representative.

Jeff Lilly is the AOC Project Manager and advisor to the PDB.



This story was posted on 2006-10-25 10:31:48
Printable: this page is now automatically formatted for printing.
Have comments or corrections for this story? Use our contact form and let us know.



Justice Center: Drawing, Side elevation from Public Parking



2006-10-25 - New Justice Center site - Photo Photo of Side Elevation, Copyright October 24, 2006, DLZ, Kentucky, Inc..
Megan Campbell-Smith, DLZ, Kentucky, Inc., showed this drawing showing the view of the Adair Justice Center side elevaton, as seen from public parking, to the Project Development Board last night. It was the first time the drawing was shown in public.

Read More... | Comments? | Click here to share, print, or bookmark this photo.



Justice Center Drawing Rear Elevation



0000-00-00 - Justice Center Site - Photo CM staff photo of Drawing Copyright October 24, 2006 DLZ Kentucky, Inc..
First time public view media view, rear elevation, Columbia Cemetery side, new Adair Justice Center. The drawing was shown to the Project Development Board at its October 24, 2006 meeting.

Read More... | Comments? | Click here to share, print, or bookmark this photo.



 

































 
 
Quick Links to Popular Features


Looking for a story or picture?
Try our Photo Archive or our Stories Archive for all the information that's appeared on ColumbiaMagazine.com.

 

Contact us: Columbia Magazine and columbiamagazine.com are published by Linda Waggener and Pen Waggener, PO Box 906, Columbia, KY 42728.
Phone: 270.403.0017


Please use our contact page, or send questions about technical issues with this site to webmaster@columbiamagazine.com. All logos and trademarks used on this site are property of their respective owners. All comments remain the property and responsibility of their posters, all articles and photos remain the property of their creators, and all the rest is copyright 1995-Present by Columbia Magazine. Privacy policy: use of this site requires no sharing of information. Voluntarily shared information may be published and made available to the public on this site and/or stored electronically. Anonymous submissions will be subject to additional verification. Cookies are not required to use our site. However, if you have cookies enabled in your web browser, some of our advertisers may use cookies for interest-based advertising across multiple domains. For more information about third-party advertising, visit the NAI web privacy site.