Pavement repairs scheduled for Interstate 65 in Bullitt County

Click on headline for full story with crossover drawing

By Andrea S. Clifford, Public Information Officer

Louisville, KY (February 26, 2014) - The Kentucky Transportation Cabinet (KYTC) recently awarded a contract for roadway improvements to Interstate 65 in Bullitt County. The $20.7 million project will involve the removal and replacement of various sections of concrete pavement across a 20-mile section of I-65.



"This project will provide a much smoother riding surface for motorists traveling both north and south on I-65," stated Matt Bullock, Chief District Engineer for the Department of Highways District 5 Office in Louisville. "While some patching and diamond grinding work has been performed in the past, this project will involve replacing any concrete slabs that are cracked or uneven due to settling."

The majority of the pavement work will take place in the right and center lanes as they have the most deterioration. Approximately 45% of the right lane, 40% of the center lane and 5% of the left lane will have the pavement replaced. This equates to approximately 40 miles of concrete pavement.

Work is scheduled to begin the week of March 10, 2014, at the Bullitt/Hardin County line and proceed north to the Bullitt/Jefferson county line. The roadway will be reduced to two lanes in each direction during most of the construction work. The speed limit will be reduced to 55 MPH in the work zone and double fines will be enforced.

Temporary median cross-overs will be used and traffic will be shifted to the southbound lanes while crews replace the pavement in the northbound lanes (see schematic below). Once that phase of work is complete, traffic will use the newly paved northbound lanes while work is performed in the southbound lanes.

Some ramps closures will be necessary during this construction with closures being restricted to weekends. Advance notice and detour routes will be provided prior to each ramp closure.

Hall Contracting of Louisville, Kentucky was awarded this contract with construction scheduled for completion in November 2014.

The date and duration of this work may be adjusted if inclement weather or other unforeseen delays occur. Dial 511 for the latest in traffic and travel information in the Commonwealth of Kentucky.


This story was posted on 2014-03-07 10:33:58
Printable: this page is now automatically formatted for printing.
Have comments or corrections for this story? Use our contact form and let us know.



 

































 
 
Quick Links to Popular Features


Looking for a story or picture?
Try our Photo Archive or our Stories Archive for all the information that's appeared on ColumbiaMagazine.com.

 

Contact us: Columbia Magazine and columbiamagazine.com are published by Linda Waggener and Pen Waggener, PO Box 906, Columbia, KY 42728.
Phone: 270.403.0017


Please use our contact page, or send questions about technical issues with this site to webmaster@columbiamagazine.com. All logos and trademarks used on this site are property of their respective owners. All comments remain the property and responsibility of their posters, all articles and photos remain the property of their creators, and all the rest is copyright 1995-Present by Columbia Magazine. Privacy policy: use of this site requires no sharing of information. Voluntarily shared information may be published and made available to the public on this site and/or stored electronically. Anonymous submissions will be subject to additional verification. Cookies are not required to use our site. However, if you have cookies enabled in your web browser, some of our advertisers may use cookies for interest-based advertising across multiple domains. For more information about third-party advertising, visit the NAI web privacy site.